Supply of gas to new Al Ain Cement plant for ARKAN
Year – 2013
Client – NPCC / ARKAN
Our Role – Sub Contractor
Scope of Work – Flow Control Valve skid installation along with all Civil, Mechanical and E&I works.
Removal of 24″ and 36″ by pass arrangements at MP 21
Year – 2013
Client – ADCO / TDW
Our Role -Sub Contractor
Scope of Work – Cold Cutting and removal of by pass lines removal of sandwich valve, installation of blind flanges, torquing, nitrogen purging of 24″ and 36″ lines.
Variation order for EPC of NEB chemical and hazardous material lay down area.
Year – 2013
Client – ADCO
Our Role – Main Contractor
Scope of Work – Construction of 1 Well cellars and 1 of mud pits each at DY-96 and DY-97 respectively for Dabiya Additional injector project.
Civil Works at GASCO-Ruwais
Year – 2013
Client -BSS TECH / GASCO
Our Role – Sub Contractor
Scope of Work – To carry out Civil / Installation / Construction scope of works for Installation, pre-commissioning and commissioning of CP systems as per GASCO standards.
Replacement of 20″ Transfer Line Portion from Remote Degassing Station (RDS2) to Central Degassing Station.
Year – 2012
Client -ADCO
Our Role – Main Contractor
Scope of Work – Replacement of 20″ Transfer line from RDS 2 to CDS including Cleaning and flushing of 6.5 km of existing line and Welding, Hydro testing of new 400m section and tie in to the existing 20″ line.
Engineering, Procurement & Construction of NEB Chemical & Hazardous Material Lay down Area
Year – 2012
Client -ADCO
Our Role – Main Contractor
Scope of Work – Construction of a shed (20m x 30m) and two paved area (30m x30m) for storing chemicals and waste skips.
Habshan 5 Utilities & Offsite Project – Structural Steel welding
Year – 2012
Client -Hyundai / GASCO
Our Role – Sub Contractor
Scope of Work – Approximately 2400 Linear Meters of Structural Steel Welding for Piping Platforms inside Habshan 5 Plant.
Civil works for permanent Telecom services at Habshan 5 Utilities & off sites Project at Habshan
Year – 2012
Client -GASCO
Our Role – Main Contractor
Scope of Work – 27 K.M of trenching including laying of FOC conduits for Etisalat Cable. This also includes 2 Nos’s of NDRC and interfacing with various Government Authorities for acquiring NOC’s
Testing and Commissioning works at Al Ain Cement Factory
Year – 2012
Client -NPCC
Our Role – Main Contractor
Scope of Work – Testing and commissioning of 48 Km 20″ pipeline to Al Ain Cement Factory.
Welding Works in ARKAN Cement Factory
Year – 2012
Client -SINOMA Equipment
Our Role – Main Contractor
Scope of Work – Welding of 115 joints of Dia 20″ at ARKAN cement factory.
ICAD BENA Factory Valve Pit & Line Replacement
Year – 2011
Client -GASCO
Our Role – Main Contractor
Scope of Work – Valve Pit & Line Replacement
Leak Testing Assembly of Metering Skid
Year – 2011
Client -GGS
Our Role – Main Contractor
Scope of Work – Welding, spectacle blinds, pipe fabrication & assembly including testing & painting, structural materials supply and fabrication including painting, miscellaneous works.
SGP Sulphur Pit Inspection & Coil Replacement
Year – 2011
Client -GASCO
Our Role – Main Contractor
Scope of Work – Full replacement of internal Steam Coils, Complete stripping of all external piping, hot insulation, (Steam, Sulphur, Condensate & all other associated external piping) Blasting, Painting & Re-insulation works. Removal & complete replacement of doors / covers located on the sulphur pit, including internal and external concrete walls repair works.
New Metering System Tie – In at GASCO Buhasa – EPC Works.
Year – 2011
Client -GASCO
Our Role – Main Contractor
Scope of Work – EPC works for phase – 1 by cutting the existing 14″ line at two locations and introducing piping arrangement of two 14″ X 12″ tees, two 14″ RB ball valves, two 12″ FB ball valves and one 2″ drain and related piping & blind flanges.
New Metering System Tie – In at GASCO ASAB -0 EPC Works.
Year – 2011
Client -GASCO
Our Role – Main Contractor
Scope of Work – EPC works for phase -1 by cutting the existing 14″ line at two locations and introducing piping arrangement of two 14″ X 12″ tees, two 14″ RB ball valves, two 12″ FB ball valves and one 2″ drain and related piping & blind flanges.
Construction Works: BC to IC Conversion Project.
Year – 2011
Client -DUSUP
Our Role – Main Contractor
Scope of Work – Procurement (Other than Client Free Issue materials), Construction and Construction related Engineering including Mechanical, Electrical and Instrumentation scope, Installation, Testing, Pre Commissioning, Commissioning Assistance of all Piping and all associated works.
Carry out Inspection & Repair as per API 650 To Water Tank 81-TK-101-B.
Year – 2010
Client -GASCO
Our Role – Main Contractor
Scope of Work – This scope of work includes carrying out MFL inspection of the Water Tank of size 20mtr dia X 10mtr heights, Repair works for the corroded plates and internal painting of the Tank.
Rehabilitation of the 67 Nos supports Welded on top of Habshan-0 Flare Piping
Year – 2010
Client -GASCO
Our Role – Main Contractor
Scope of Work – This Scope of Work covers lifting of supports, scaffolding, application of blasting / painting on support plates / affected area on top of flare line, application of Belzona 1121, settling back of supports, finishing of the support plate / pipe gaps with Belzona and final painting on support plates.
Removal of 10″ Gas Pipeline in Ghantoot area.
Year – 2010
Client -GASCO
Our Role – Main Contractor
Scope of Work – This Scope of Work covers Demolition work for 8Km long 10″dia Pipeline including demolition of delivery point station, pig launcher and its associated facilities.
Removal of Gas facilities at Mirfa Power plant.
Year – 2010
Client -GASCO
Our Role – Main Contractor
Scope of Work – Demolition of 8 km long 4” dia Pipeline including demolition of CRS and Pig launcher station.
Removal of 24” Maqta- ADPS Pipeline.
Year – 2010
Client -GASCO
Our Role – Main Contractor
Scope of Work – Removal of 2.7 Km long 24” dia Gas Pipeline inside Umm-Al- Nar Refinery including de-commissioning of 22 Km long Maqta – ADPS Pipeline and Quick shut down.
Re-Routing of the 2” Gas Supply to Baynunah PRS station in mena
Year – 2009
Client -GASCO
Our Role – Main Contractor
Scope of Work – Piping and structural work.
Laying of High Pressure Tubing & Control Cable & for Painting of Compressor Building.
Year – 2009
Client -Bauer Kompressoren
Our Role – Sub Contractor
Scope of Work – a) High Pressure Tubing & Control Cable laying.
b) Painting of Compressor Room.
c) Other Finishing Works.
6″ High pressure Gas Pipeline to Gulf Sponge Iron Factory.
Year – 2009
Client -GASCO / Gulf Sponge Iron
Our Role – Main Contractor
Scope of Work -18″ x 6″ Cold Tapping work, technical services for Gas Pipeline installation.
Natural Gas Extension to Ajmal Steel Factory.
Year – 2008
Client -GASCO / Ajmal Steel
Our Role – Main Contractor
Scope of Work – Supply and Installation of 4″ dia Gas Pipeline 0.5 km long including hot tap.
EGDS Upgrade works – Civil & FOC works.
Year -2007-2008
Client – Dolphin Energy / Punj Lloyd
Our Role – Sub Contractor
Scope of Work – 1) Supply and installation of safety signs and fencing.
2) Installation crash barriers for GASCO Pipeline network in Eastern Area.
EPC of Cathodic Protection of Well Casings in ADCO Fields (Buhasa/Huwailia).
Year -2007
Client – ADCO / BSS Technologies
Our Role – Sub Contractor
Scope of Work – Civil / Installation / Construction works for Cathodic Protection of Well Casing
4″ Dia Pipeline for Natural Gas Extension to Plot No 21B3 & 22B3 in ICAD 1.
Year – 2007
Client – GASCO / QEnergy
Our Role – Sub Contractor
Scope of Work – 4″ x 850 Meters long On Shore Buried Gas Pipeline including Hot Tapping with Gasco Pipeline Network (Pipes & Skid free issued)
Onshore Fuel Oil Pipeline for filling of MFO Tanks 5&6.
Year – 2007
Client – Sharjah Electricity & Water Authority (SEWA)
Our Role – Main Contractor
Scope of Work – 10″ dia x 1.01 km long On Shore Buried Oil Pipeline
Gas Supply to Al Ain Air College.
Year – 2006-2007
Client – GASCO/ Toledo
Our Role – Sub Contractor
Scope of Work – 1) 8 Km of Pipeline corridor fencing.
2) 4.5 Km of Pipeline berm construction.
3) Technical services for 30″ x 4″ Hot Tap connection.