Operation & Maintenance – Al Ain Cement Factory
Client – Al Ain Cement Factory
Project Reference – SWO – 5000000177
Scope of Work – Monitoring of Launcher, Receiver stations & patrolling of Approximately 47 kilometer pipeline.
Facilities Maintenance Services: Pipeline and Systems Maintenance
Client – Dolphin Energy
Project Reference – NC-UOP-046(B) TO # 21 P1 RS
Scope of Work – Installation of 863-PCV-006 at UOBS
Facilities Maintenance Services: Right of Way Maintenance
Client – Dolphin Energy
Project Reference – NC-UOP-048(D) TO # 29 P3 RS
Scope of Work – UOP House Keeping
Project Reference – NC-UOP-048(D) TO # 32 P3 RS
Scope of Work – ROW miantenance works due to Rain at AFP and TFP
Facilities Maintenance Services: Building General Maintenance
Client – Dolphin Energy
Project Reference – NC-UOP-047(C) TO # 02
Scope of Work – HVAC System Upgrade
Operation & Maintenance – GASCO
Client – GASCO
Project Reference – SWO 5040199
Scope of Work – Emergency Operation & Maintenance Services (EOM) for ICAD Facilities.
Project Reference – Agreement No: 158633101/2010
Scope of Work – Carryout Inspection & Repair as per API 650 to Water Tank 81-TK-101B
Project Reference – SWO – ITT No: 1590371
Scope of Work – Supply, Installation & Welding of Split Sleeve on 16″ Habshan Ruwais Condensate Pipeline
Project Reference – Agreement No: 144318
Scope of Work – Supply, Installation & Welding of Split Sleeve on 16″ Habshan Ruwais Condensate Pipeline
Project Reference – SWO 131045.101
Scope of Work – Emergency Repair Work on 30″ BAB – MAQTA Gas Pipeline
Project Reference – SWO 126883
Scope of Work – 81-TK-101 A, API 650 Water Tank Inspection & Repair
Facilities Maintenance Services: Pipeline and Systems Maintenance
Client – Dolphin Energy
Project Reference – NC-UOP-046(B) TO # 20 P1 RS
Scope of Work – Servicing of Valves
Project Reference – NC-UOP-046(B) TO # 18 P1 RS
Scope of Work – Installation of valves – TFP projects
Project Reference – NC-UOP-046(B) TO # 19 P1 RS
Scope of Work – Assistance for PV maintenance at TRF
Project Reference – NC-UOP-046(B) TO # 16
Scope of Work – Passive Shelter Repair SV1, SV 2 & SV6
Project Reference – NC-UOP-046(B) TO # 17
Scope of Work – Instrument air compressor repair works
Project Reference – NC-UOP-046(B) TO # 09
Scope of Work – Repairing of Air Compressor in TRF
Project Reference – NC-UOP-046(B) TO # 10
Scope of Work – Qidfa UFM Calibration
Project Reference – NC-UOP-046(B) TO#11
Scope of Work – TRF Heater Modification 860-101/201/301
Project Reference – NC-UOP-046(B) TO#12
Scope of Work – Inergen Cylinder Testing
Project Reference – NC-UOP-046(B) TO # 02
Scope of Work – Monitoring & Control of DEL Facilities on 30” MAQTA-AL-AIN Gas Pipeline at SV6 & SV9
Project Reference – NC-UOP-046(B) TO # 01 Rev.1
Scope of Work – Modification of Inergen System at LCR Taweelah, Replacement of Existing Manual Call point by New Explosion Proof ESD Pushbutton, Cable Laying and Termination for F&G, HVAC, Modification of FACP Panel.
Project Reference – NC-UOP-046(B) TO # 03
Scope of Work – Repair of Rectifier Unit at jebel Ali and Replacement of CP Rectifier Controller Unit at SV3, Maqta jebel Ali Pipeline.
Project Reference – NC-UOP-046(B) TO # 04
Scope of Work – CP Cable Replacement & Shed for Junction Box
Project Reference – NC-UOP-046(B) TO # 05
Scope of Work – SV Solar System Replacement
Project Reference – NC-UOP-046(B) TO # 06
Scope of Work – CIPS & DCVG for 36” Maqta to Umm Al Nar U/G Pipeline
Project Reference – NC-UOP-046(B) TO # 07
Scope of Work – Metering Maintenance Network & Installation of O2 Analyzer
Project Reference – NC-UOP-046(B) TO # 08
Scope of Work – Maqta RTU Segregation
Facilities Maintenance Services: Right of Way Maintenance
Client: Dolphin Energy
Project Reference – NC-UOP-048(D) TO # 31 P3 RS
Scope of Work – ROW maintenance works due to Rain
Project Reference – NC-UOP-048(D) TO # 30 P3 RS
Scope of Work – Washout near Al Ain Station due to TRANSCO Pipe Burst
Project Reference – NC-UOP-048(D) TO # 28 P3 RS
Scope of Work – Emergency works Transco wash out
Project Reference – NC-UOP-048(D) TO # 27 P3 RS
Scope of Work – Installation of Perimeter Fence at Tie-in Station (KP 42+900 MJPL)
Project Reference – NC-UOP-048(D) TO # 26 P3 RS
Scope of Work – Fencing at Qidfa Station
Project Reference – NC-UOP-048(D) TO # 24 P3 RS
Scope of Work – Pipe stack and Lay down area in Al Ain
Project Reference – NC-UOP-048(D) TO # 25 P3 RS
Scope of Work – ROW repair works for Al Ain-Fujairah Pipeline (AFP) and Taweelah-Fujairah Pipeline (TFP)
Project Reference – NC-UOP-048(D) TO # 22
Scope of Work – Exposed Maqta Al Ain Pipeline repair
Project Reference – NC-UOP-048(D) TO # 12
Scope of Work – Fence repair Between SV 6 and SV 7 on MAP
Project Reference – NC-UOP-048(D) TO # 14
Scope of Work – ROW Maintenance and Fence Repair
Project Reference – NC-UOP-048(D) TO # 15
Scope of Work – UOP House Keeping
Project Reference – NC-UOP-048(D) TO # 16
Scope of Work – Washout Repair at Al Ain Station due to TRANSCO Pipe Burst
Project Reference – NC-UOP-048(D) TO # 01
Scope of Work – TRF Assembly Point
Project Reference – NC-UOP-048(D) TO # 02
Scope of Work – Washout Repair at Al Ain Fujairah Pipeline KP .500 due to damaged pipeline of TRANSCO
Project Reference – NC-UOP-048(D) TO # 03
Scope of Work – Fence Modification Works on Maqta – Jebel Ali Pipeline
Project Reference – NC-UOP-048(D) TO # 05
Scope of Work – ROW & Fence Maintenance on Al Ain – Fujairah Pipeline
Project Reference – NC-UOP-048(D) TO # 06
Scope of Work – Al Ain Station Flooding
Project Reference – NC-UOP-048(D) TO # 08
Scope of Work – ROW maintenance (Maqta – jebel Ali Pipeline)
Project Reference – NC-UOP-048(D) TO # 09
Scope of Work – Al Ain – Fujairah Line wash out at KP 0 + 500
Project Reference – NC-UOP-048(D) TO # 01 R1
Scope of Work – Re-instatement of wash out area at KM 135.4 of Al-Ain – Fujairah Pipeline
Facilities Maintenance Services: Provision of Labour, Equipment & Materials
Client: Dolphin Energy
Project Reference – NC-UOP-049 (C) TO # 05 P4 RS
Scope of Work – Manpower and equipment for Pigging activities Maqta and TRF
Project Reference – NC-UOP-049 (C) TO # 01
Scope of Work – Hire of Shovel
Project Reference – NC-UOP-049 (C) TO # 02
Scope of Work – Hire of Air Compressor on Weekly Basis
Facilities Maintenance Services: Building General Maintenance
Client: Dolphin Energy
Project Reference – NC-UOP-047(C) TO # 01
Scope of Work – Supply and Installation of 5 Meter wide Gate along with 1 meter Man access Gate.