EPC works for Additional MPSVs
Year – 2022
Client – ADNOC Onshore
Our Role – EPC Contractor
Scope of Work – EPC works for the provision of 4 No’s of Multiport Selector Valves (MPSV), 2 No’s of MPFM with ESD and field instruments. All associated Piping and Tie-in Works, Civil works, Electrical Works, Instrumentation and Control works, NDT Works, Pre-commissioning and Painting Works.
Supply of Resources for Well work over preparation & Tie-in activities for ADNOC Onshore Assets
Year – 2022
Client – ADNOC Onshore
Our Role – EPC Contractor
Scope of Work – The project scope includes the supply of resources to perform dismantling and re-instatement (Tie-In) of Well Head Facilities like piping & associated surface facilities up to 100 – 120 meters for Oil, Water, Gas wells, WAG/GLFT/ESP wells from Well Head X-mas trees for all ADNOC Onshore Assets (BAB, Bu Hasa, Asab, Sahil, SQM)
EPC for BAB Facilities Upgrade Project
Year – 2022
Client – ADNOC Onshore
Our Role – EPC Contractor
Scope of Work – The project scope consists of four packages including Engineering, Procurement, Construction, Pre-commissioning and Commissioning works for:
1. PACKAGE 1: BCDS Flow lines Decongestion
2. PACKAGE 2: BAB SIMGAP EOR Pilot Project
3. PACKAGE 3: BAB TH (B) Gas injection system Holistic
4. PACKAGE 4: EPC for 4 Additional Artificial Lift Wells
EPC for Al Dabbiya (Al Nouf) Thamama B Transition Zone Developments-Phase II
Year – 2021
Client – ADNOC Onshore
Our Role – EPC Contractor
Scope of Work – The project scope consists of Engineering, Procurement and Construction of 2 new clusters including 1 no of Offshore cluster, Works at the existing cluster, Tie-in of 33 wells, 35 Km of pipeline Construction Works and associated Civil, Electrical, Instrumentation works at Al Nouf.
EPC for AIG Mirfa Train Interconnection Project
Year – 2021
Client – ADNOC Onshore
Our Role – ADNOC Linde Industrial Gases
Scope of Work – The project scope consists of Engineering, Supply, Fabrication, Installation, Inspection, Testing and Pre-Commissioning of new Interconnecting Piping and MOV’s between Train 1 & 2.
Technical Services Agreement (Call-Off) for Bu Hasa Tie-Ins (2021-25) Package 2
Year – 2021
Client – ADNOC Onshore
Our Role – EPC Contractor
Scope of Work – The project scope consists of Engineering, Procurement and Construction of 104 no’s of various type of Wells at On Pad/Off Pad and 153 KM of Flowline Construction Works (U/G and A/G) at Bu Hasa.
Construction of Flowlines and Wellhead Tie-in installations for conventional wells at ADNOC Onshore Fields-Package B (BAB)
Year – 2020
Client – ADNOC Onshore
Our Role – EPC Contractor
Scope of Work – The project scope consists of Engineering, Procurement and Construction of Flowlines and Wellhead installations across the ADNOC Onshore Oil Field at BAB (152 No’s of Oil Producer Wells, 138 No’s of Water Injection Wells and 2,092 Km flow lines)
EPC for Fire Water Ring Replacement at MOT & MPS
Year – 2020
Client – ADNOC Onshore
Our Role – EPC Contractor
Scope of Work – The project scope consists of Engineering, Procurement and Construction of above ground fire water pipe with internal FBE coating, concrete foundations, Structural installation, Soil improvements at foundation locations, demolition & removal of existing underground GRE pipe and associated Electrical and Instrumentation works.
EPC for Upgrade of MP-21
Year – 2020
Client – ADNOC Onshore
Our Role – EPC Contractor
Scope of Work – The project scope consists of Engineering, Procurement and Construction of 2 no’s of Fire Water Storage Tanks, Fire Water pumps, Jockey pumps, Diesel Tank, MOV’s GRE piping and associated Electrical and Instrumentation works.
Call-Out Works Contract for ASR GAS Tie-Ins in BAB
Year – 2020
Client – ADNOC Onshore
Our Role – EPC Contractor
Scope of Work – The project scope consists of Engineering, Procurement and Construction of 09 No’s of wells at BAB (6 No’s for Gas Producer Wells, 3 No’s of Gas Injector Wells and re-routing of 20 no’s of Flowline)
Pre-Works and Pipeline Works at Bu Hasa Integrated Field Development (BUIFD) Project
Year – 2018
Client – ADNOC Onshore / TECNICAS REUNIDAS S.A
Our Role – Sub Contractor
Project Scope Includes – Pre-Works And Main Pipeline construction works for approx. 811 Kms of Pipelines/ Flowlines of various diameters 24”/20”/18”/16”/12”/10”/8”/6”/4”/3” including Construction of 5 nos. of Block Valve stations.
Pre-Works Includes: De-Oiling, flushing, Re-routing & demolition of existing A/G Oil Flowlines & Water Injection lines / Under Ground Gas Injection Flowlines and Tie-ins and Relocation of existing Solar/WHCP panels, Rerouting of existing OFC/Sand tracks/Rig Roads.
Main Pipeline Works Includes: ROW construction, A/G and U/G Pipeline Construction Horizontal Directional Drilling Crossings (NDRC), Open Cut Crossings, Hydro Testing for Pipelines, Pre-commissioning Works including Cleaning, Gauging, Flushing, Swabbing, Drying, Caliper Pigging and Intelligent Pigging. FOC laying, Cathodic Protection (CP) Works.
Construction of Flowlines and Wellhead Tie-In Installations in ADCO’s Fields – Package C
Year – 2017
Client – ADNOC Onshore
Our Role – Main Contractor
Scope of Work – The project packages include Engineering, Procurement, Construction, Pre-commissioning and Commissioning works for 118 Nos Natural Flowing Oil Wellheads, 77 Nos Water Injection Wellheads, 420 Km of Flowline and 40 Nos Replacement of Wellhead Control Panels.